Research shelf / Materials & engineering / AusDike™

Materials & engineering

A flood barrier that gets stronger the deeper the water gets

A sealed flood barrier fights the full hydrostatic load. An open-bottom one lets the water in underneath, so the pressure equalises across both faces and the net lateral force drops by 73%. The panel gets its ballast from the thing it is holding back. The engineering question is then whether a 9 mm polypropylene wall can take the column load, and 28 simulations say yes with margin.

Design document AGPL-3.0+ / commercial
Evidence level

Specified in detail; implementation partial or absent.

FolderPlastic Products
FieldMaterials & engineering
StatusConcept feasibility plus simulation closure. No physical prototype, no certification.
What it is

An open-bottom self-ballasting levee panel taken from concept to tooling quote — 28 simulations, a buckling-governed wall, and one adverse finding the programme did not bury.

The panel is 600 × 300 × 560 mm, injection-moulded, ~15 kg empty — a two-person carry with no tools and no machinery. A 50 m run deploys in about ten minutes with two operators. The design intent is a domestically produced Australian competitor to imported steel and HDPE deployable barrier systems.

The engineering programme’s central finding is that the wall is column-buckling-governed rather than bending-governed. That changed the design: thickness went from 8 mm to 9 mm on the strength of analytical Euler and 20-element eigenvalue FEA agreeing to 0.0% error, and the polymer specification tightened from neat recycled polypropylene to 15% talc-filled rPP with HALS UV stabiliser, lifting heat-deflection temperature from 55 °C to 85 °C to cover Brisbane solar service.

At final spec the panel carries a 4.9× tipping safety factor and 2.1× sliding on a two-stack 600 mm flood with no bracing, anchors or flanges; column buckling is 15.7×; Miner’s-rule fatigue damage at 25 years is 0.00975, a 103× life margin. Costing is from first principles at A$65.51 per panel against a A$109/linear-metre target, with tooling breakeven at 3,500 panels.

The wind finding is why this reads as engineering. A feasibility study that reports only favourable numbers is marketing. This one states that empty panels tip above 35 m/s and turns that into a deployment protocol constraint rather than a footnote. The 4.9× tipping margin is more credible because the 35 m/s failure is printed next to it.
Claims ledger

Every number, and what stands behind it

A claim is only worth the evidence attached to it. Each row below carries its basis: measured on the author’s own hardware, derived from the construction, measured on synthetic data, projected from literature, or simply cited.

Breakdown of this page’s claims by what stands behind each one
scroll to see the whole chart →
Every claim, weighted by its evidence. The table below is the same data row by row.
ClaimFigureBasisContext
Net lateral force reduction73%DerivedOpen-bottom self-ballasting vs a sealed cell
Empty panel mass~15 kgDerivedTwo-person carry, no tools
Deployment rate50 m in ~10 min, two operatorsProjectedFrom panel handling time
Tipping safety factor4.9×SyntheticTwo-stack 600 mm flood, no bracing or anchors
Sliding safety factor2.1×SyntheticSame load case
Column-buckling safety factor15.7×SyntheticEuler analytical and 20-element eigenvalue FEA agree to 0.0%
25-year fatigue damage0.00975 (103× margin)SyntheticMiner’s rule
Heat-deflection temperature55 °C → 85 °CDerived15% talc-filled rPP with HALS, for Brisbane solar service
First-principles COGSA$65.51 per panelDerivedMaterial, machine time, labour, 35% overhead
Price vs nearest competitor42% cheaperProjectedA$109/m against Boxwall NZ at ~A$180/m
Tooling breakeven3,500 panelsDerivedAgainst A$382,500 advanced-tooling capex
Annual capacity, one machine59,750 panels (A$6.2 M)Projected300-tonne machine, two shifts
Adverse finding — wind stabilityempty two-stack fails above 35 m/sSyntheticMandates a pre-fill-or-stake protocol

Measured — author-run experiment on the stated setup. Synthetic — measured, but on synthetic rather than real data. Derived — follows from the stated construction or proof. Projected — paper-stated projection, not an author-run benchmark. Cited — taken from external literature.

Methods

How it works

  • Open-bottom self-ballasting. Floodwater enters the panel base and equalises pressure across both faces — the barrier is ballasted by the flood.
  • Dual-method buckling check. Analytical Euler and 20-element eigenvalue FEA, agreeing to 0.0% — which is what justified the 8 → 9 mm change.
  • Four-SKU family. Standard, cold-climate, mine-chemical and 90° corner variants derived from the same simulation set.
  • First-principles costing. COGS built from material, machine time, labour and overhead rather than quoted.
Stated limitations

What it does not do

Taken from the folder’s own README. Nothing here has been softened.

  • No physical prototype exists. The programme classifies itself as concept feasibility plus engineering-simulation closure, and nothing more.
  • Empty two-stack panels lose tipping stability above 35 m/s wind. This is the programme’s own adverse finding and it constrains the deployment protocol.
  • Polypropylene is incompatible with petroleum and hydraulic-oil bunding, which is why the mine SKU has to be HDPE.
  • PP Izod impact halves at 0 °C, which is why the cold SKU has to be rubber-toughened rTPP.
  • SES procurement cycles and NATA-laboratory AS/NZS certification are named as unresolved commercial risks.
Use it

Free under AGPL-3.0+ for almost everyone

Personal use, charities, education and organisations under AUD 50,000 a year pay nothing. A tiered commercial licence covers everyone else.